今日看料

Construction

Fri September 20 2024

Related Information

Kijlstra helps save time and space

7 Apr 11 A pre-fabricated Combined Sewer Overflow (CSO) chamber from precast drainage manufacturer Kijlstra, has helped contractor Clancy Docwra cut installation times and minimise disruption during a flood alleviation project for Scottish Water Solutions.

The scheme involved upsizing the surface water drainage system and installing a CSO to protect homes in Kingsknowe Road North, located in the residential area of Saughton, Edinburgh.

The 36-tonne CSO base unit, measuring 4.1 m x 2.5 m x 2.0 m, was lifted into place in one piece. Once all connections had been made, the concrete cover, weighing another 10 tonnes, was then grouted on top. The excavation was then back-filled and the road surface reinstated.

The new CSO allows for the foul sewer to flow into the surface water sewer through a screen, thereby avoiding any surcharge of effluent. In the past, heavy rain has caused the foul sewer to overflow and flood a number of houses in the street.

Installing the CSO and enlarged sewer meant significant excavation in the highway and potentially massive disruption to traffic and residents. Although not a major thoroughfare, the road is relatively narrow and is on a busy bus-route.

The use of a traditional in-situ concrete CSO would have required a large excavation which would have had to remain open while the formwork was assembled and the concrete poured. This excavation would have had to remain open until the concrete had cured and the formwork removed 鈥 a period of up to two weeks.

Related Information

鈥淪peed of installation was a major factor in choosing the Kijlstra CSO鈥 explains Scott Heath, senior project manager with Clancy Docwra. Installing the Kijlstra CSO only required the excavation to remain open long enough for the unit to be craned in, the cover installed and the necessary connections to be made.

Instead of the two weeks required for the conventional method, Kijlstra鈥檚 CSO was delivered and installed in a single day. But speed of installation was not the only advantage, says Mr Heath:

鈥淏ecause the CSO was pre-cast we could reduce the size of the excavation which was a key factor given the amount of services located within the area鈥 he says.

鈥淚鈥檇 never used Kijlstra鈥檚 pre-cast units before鈥 concludes Mr Heath, 鈥渂ut after this job I鈥檇 definitely consider using them for future projects鈥.

Got a story? Email news@theconstructionindex.co.uk

MPU
MPU

Click here to view latest construction news »