今日看料

Construction

Fri September 20 2024

Related Information

Thyssenkrupp Elevator builds US test tower

19 May 20 Thyssenkrupp Elevator has completed the core of its 128m-tall US test tower ahead of schedule in 57 days.

photo by Ron Acord
photo by Ron Acord

The test tower is part of Thyssenkrupp Elevator鈥檚 new North American headquarters at The Battery Atlanta.

Slip-form construction was used to create the core of the tower at a rate of more than 2.1m per day.

The Innovation and Qualification Center (IQC) and adjacent Corporate Headquarters (CHQ) are on schedule for completion in 2021 with final move-in by early 2022.

鈥淭he completion of the IQC slip-form process is an important moment in our company鈥檚 history as it not only symbolises a brighter future for our organization and the local community, but will be a beacon of engineering excellence that will help transform an industry in need of modern innovations,鈥 said Thyssenkrupp Elevator CEO Peter Walker.

Slipform had also been used for Thyssenkrupp鈥檚 244m-tall elevator test tower in Rottweil, Germany, though is relatively rare in the USA.

Related Information

Construction of thyssenkrupp Elevator鈥檚 new test tower, including the slipform construction, is being handled by its general contractor, Brasfield & Gorrie. Subcontractor Gleitbau 鈥 Salzburg provided the design, engineering and oversight over the slipform construction process.

鈥淪elf-performing concrete work is one of Brasfield & Gorrie鈥檚 areas of expertise, and it gives us superior control over the cost, quality, and schedule of a project,鈥 said Brasfield & Gorrie vice president and division manager Ben Norton. 鈥淲e constantly seek opportunities to innovate so we can better serve our clients, and the slip-form process has allowed us to maximize efficiency while building this quality concrete 蝉迟谤耻肠迟耻谤别.鈥

The test tower, which has 18 shafts, will be used to trial new concepts and product pilots, including high-speed elevators and Twin, the company鈥檚 system that features two cabins working independently in one shaft. The IQC will also test Multi, Thyssenkrupp鈥檚 rope-less and sideways-moving elevator system. In addition, the test tower will also conduct tests to ensure compliance with safety requirements for standard elevators.

To showcase the elevators at the test tower, the IQC will feature a glass exterior fa莽ade, allowing visitors y to view operations that are normally hidden behind concrete walls. In addition to the elevator test tower, the IQC will also feature event and meeting spaces located at the top of the building as well as a digital showroom, software lab, engineering offices and training facilities.

Got a story? Email news@theconstructionindex.co.uk